Corrections

Every number on this site comes from a document I can point to:

Spotted a mistake, or have a document I should see? Write to daredavil239804@gmail.com with the page, the claim and, if you can, a source. I reply within 7 days and note every fix on the page.

Email a correction

Share this page

Please check the linked source before you forward a figure.

Layered forested ridges of the Sahyadri at Mahabaleshwar
The Sahyadri at Mahabaleshwar, Satara · Photo: Wikimedia Commons

Story

What pumped storage asks of the Sahyadri

The trees, the species, the clearances, the villages and the case for the projects, in 10 short chapters. Every number links to its document. Pick a chapter, or start at the top. New to pumped storage? See how it works.

  1. 148,557 trees
  2. 2What lives here
  3. 3The forest bill
  4. 4How the review was sidestepped
  5. 5Imposed, not designed
  6. 6The promise
  7. 7A battery that can burn coal
  8. 8Built, not used, and cheaper options
  9. 9What supporters say
  10. 10What I ask for

Chapter 1

48,557 trees

Above the village of Potal in Karjat taluka, the Sahyadri rises in a wall of forest towards the Saidongar plateau. On the forest committee's paper it is 233ⓘ hectares of forest land. On the ground it is a slope of trees, scrub and grass that turns green with the first rain, and the upper edge of a valley that six villages depend on.

Torrent Power wants to put a 3,000ⓘ MW pumped storage project here: two reservoirs, one on the plateau and one on the Pej river below, joined by tunnels. Water is pumped up when power is cheap and let down through turbines when it is dear. The project needs 377ⓘ hectares in all.

How many trees?

Nobody outside the Forest Department knows exactly. Three official numbers exist, and they do not agree.

1 dot = 10 trees
48,557Documented“Also, the proposal involves felling of 48557 number of trees.”FAC minutes, 2 Dec 2025 (Stage-I recommended): trees to be felled, page177 · 2 December 2025 Documented

FAC minutes, 2 Dec 2025 (Stage-I recommended)

48,000Documented“clearing of 48,000 nos. of trees. (Trees proposed for plantation on Muck disposal area also”Torrent's draft EIA (Aug 2025): trees to be cut for the project, page21 · August 2025 Documented

Torrent's draft EIA (Aug 2025)

32,490Reported“…Pawar Oppose Cutting Of 32,490 Trees For Karjat Power Project A forest order dated October 14, 2026, reportedly permits felling 32,490 trees in Karjat forests for Torrent Power’s proposed 3,000 MW Saidongar-I project. Commenting on the opposition criticism, state…”FPJ (citing TOI): felling permission of 14 Oct 2026 · 25 October 2026 Reported

FPJ (citing TOI)

Data table
SourceTrees
FAC minutes, 2 Dec 2025 (Stage-I recommended)48,557
Torrent's draft EIA (Aug 2025)48,000
FPJ (citing TOI)32,490
  • 48,557ⓘ trees. This is the count in the minutes of the Forest Advisory Committee, the Union environment ministry's panel that recommended Stage-I forest clearance on 2 December 2025. Documented
  • About 48,000ⓘ. This is Torrent's own estimate in its draft EIA of August 2025. The same summary describes the forest as "shrub and grass dominated" with "very sparse" small trees. Documented
  • 32,490ⓘ. This is the number reported from a Forest Department felling permission dated 14 October 2026. The order itself has not been made public. Reported

No public document explains why the permission covers so many fewer trees than the committee counted. A phased approval is one possible reason; I have not been able to confirm it.

Activists say even the highest figure is too low. Adv. Kailash More of the Karjat Taluka Paryavaran Bachao Samiti told ThePrint that the number actually being cut is several times what is on paper. Alleged No survey has tested that claim, and none is public.

I show these numbers side by side, and do not average them.

Cleared inside a reserve that does not exist yet

The same committee minutes record that 197.77ⓘ of the 233ⓘ hectares lie inside the proposed Rajmachi Conservation Reserve, and inside the Western Ghats ESA in the draft of July 2024. Documented Neither has been notified. The committee recommended Stage-I clearance anyway, and told the developer to seek approval again if the reserve is ever notified. The ministry granted Stage-I on 31 December 2025, and the EC followed on 12 January 2026.

The forest that is lost is to be "compensated" with 252.76ⓘ hectares at Kemase and Dhankal in Patan taluka of Satara, after the first site fell through. That land is already forest-like, and it sits in the buffer of Sahyadri Tiger Reserve. Documented Compensatory afforestation there plants trees among trees, a district away.

Felling, then a halt

Felling began around Dussehra. On 26 October, at a press conference in Mumbai with actor Sayaji Shinde, Adv. More alleged that hundreds of trees were coming down every day. Alleged Aaditya Thackeray visited Saidongar and called it a "massacre of nature". Reported Chief Minister Devendra Fadnavis said the project had completed all approvals and that local concerns would be considered. Official claim

On 27 October the Forest Department said felling had stopped. Reported It has not said how many trees were already cut, or whether the halt is formal. Prime Minister Narendra Modi is scheduled to lay the foundation stone on 3 November.

  1. Clearance MoEFCC final approval for 233 ha forest diversion at Karjat (reported) ReportedNot yet reviewed
  2. Felling Forest order permits felling of 32,490 trees for Karjat PSP Reported
  3. Felling Political opposition to felling of 32,490 trees at Karjat Reported
  4. Protest Actor Sayaji Shinde, activists call for statewide protest over Karjat felling Alleged
  5. Protest Opposition leaders visit Sai Dongar; CM calls criticism a 'fake narrative' Reported
  6. Felling Tree felling at Saidongar halted after protests Reported
  7. Construction Scheduled: PM to lay foundation stone for Karjat PSP Reported

Not only Karjat

Karjat is the project where trees are falling first, not the only one where they will fall. The committee papers for Tata Power's Shirawta project record 64,729ⓘ trees, on forest with a canopy density of 0.7ⓘ, which the forest survey classes as very dense. Documented Adani's Malshej Ghat project at Bhorande counts about 35,000ⓘ trees, Torrent's second project at Maval 9,554ⓘ, and Tata's Bhivpuri 6,834ⓘ.

Together, the projects that have published a tree count add up to 1,64,674 trees on record. Most projects in the pipeline have not published one at all.

Did you know?

The forest committee that cleared Karjat recorded 48,557 treesDocumented“Also, the proposal involves felling of 48557 number of trees.”FAC minutes, 2 Dec 2025 (Saidongar-1 Stage-I), page177 · 2 December 2025 to be felled on 233 haDocumented“…te Change to review the project’s environmental implications. The organisation has raised concerns over the proposed diversion of 233 hectares of forest land, warning of potential impacts on the Saidongar area’s natural resources, wildlife and local communities.…”FPJ (citing TOI): felling permission of 14 Oct 2026 · 25 October 2026; Torrent's own draft EIA said 'about 48,000Documented“clearing of 48,000 nos. of trees. (Trees proposed for plantation on Muck disposal area also”Saidongar-1 draft EIA executive summary (MPCB), page21 · August 2025'. The felling permission reported in Oct 2026 is for 32,490Documented“…Pawar Oppose Cutting Of 32,490 Trees For Karjat Power Project A forest order dated October 14, 2026, reportedly permits felling 32,490 trees in Karjat forests for Torrent Power’s proposed 3,000 MW Saidongar-I project. Commenting on the opposition criticism, state…”FPJ (citing TOI): felling permission of 14 Oct 2026 · 25 October 2026.

Documented Source: FAC minutes, 2 Dec 2025 (Saidongar-1 Stage-I) · FPJ (citing TOI): felling permission of 14 Oct 2026 · Saidongar-1 draft EIA executive summary (MPCB)

Chapter 2

What lives here

A tree count is the easiest thing to measure and the least of what is lost. The Sahyadri is not a stand of trees. It is a living system of forest, plateau, river and grove, and these projects cut into all four.

A corridor, not a fenced park

Torrent says the Karjat site is 16ⓘ km from Bhimashankar Wildlife Sanctuary and outside its eco-sensitive zone. Official claim On a map of legal boundaries, that is true. On a map of where animals move, it is not the point.

Karjat lies on the forest belt that links Bhimashankar to Malshej Ghat and on to the rest of the northern Sahyadri. Reported Leopard, sambar, gaur, langur and the Shekru, the Indian giant squirrel that is Maharashtra's state animal, use this belt. The Shekru lives in the canopy and travels from tree to tree; a reservoir or a cleared transmission line is a wall to it.

The project's own EC lists 14ⓘ Schedule-I mammals in its study area, including leopard, sloth bear, Indian wolf, four-horned antelope and pangolin, and orders a plan for human–animal conflict. Documented Schedule-I is the highest protection Indian wildlife law gives. A project that needs a conflict plan for its neighbours is not far from wildlife.

Further north, THDC's Malshej project is about 3ⓘ km from Kalsubai-Harishchandragad Wildlife Sanctuary, and its upper reservoir at Khubi sits on the corridor between Harishchandragad and Bhimashankar. Reported To the south, Adani's Nivakane project is about 150ⓘ metres from the buffer of Sahyadri Tiger Reserve. Documented

Saidongar-1 PSP, Karjat · Forest clearance granted Saidongar-2 PSP, Maval · Study terms approved (ToR) Bhivpuri PSP · Under construction Shirawta PSP · Environmental clearance granted Bhira PSP (existing) · Operating Ghatgar PSP (existing) · Operating Bhavali PSP · Forest clearance deferred Pane PSP · Environment clearance recommended Malshej Ghat Bhorande PSP · Study terms approved (ToR) THDC Malshej Ghat PSP · Study terms approved (ToR) JSW Bhor–Mahad PSP (5,400 MW) · Study terms approved (ToR) Tarali PSP · Environmental clearance granted Warasgaon–Warangi PSP · Rejected, resubmitted Patgaon PSP · Study terms lapsed (ToR) Koyna–Nivakane PSP · Environment clearance recommended Pimpalpada–Savale PSP · Study terms approved (ToR) Kumbhe PSP · Study terms approved (ToR) Ambegaon PSP · Study terms approved (ToR) Savitri PSP · Study terms approved (ToR) Kamod PSP · Study terms approved (ToR) Adnadi PSP (Chikhaldara) · Study terms approved (ToR) Amba PSP · Study terms approved (ToR) Aruna PSP · Study terms approved (ToR) PEN Off-Stream PSP · Study terms approved (ToR) Tilari PSP · Study terms approved (ToR) Pawana Falyan PSP · Study terms approved (ToR) Kolhapur PSP (Chandgad) · Study terms approved (ToR) Nayagaon PSP (Soygaon) · Study terms approved (ToR) Ghosla PSP · Study terms approved (ToR) Humbarli Birmani PSP · Study terms approved (ToR) Aruna Kolamb PSP · Study terms approved (ToR) Ghatghar PSP Stage II · Study terms deferred (ToR) Kalu PSP · Study terms approved (ToR) Ranavadi PSP · Study terms approved (ToR)
Locator only: dots are placed by latitude and longitude. A full map with forests and protected areas comes later.

Sanctuary or national park boundaryEco-sensitive zone (dashed: proposed) Pumped storage project

Map tiles, boundaries and village points from OpenStreetMap (ODbL). Boundaries are as mapped by OSM volunteers, not the gazette notification; no corridor boundary is published. © OpenStreetMap
Data table
ProjectNearest protected areakm
Ghatghar PSP Stage IIKalsubai-Harishchandragad WLS0
Koyna–Nivakane PSPSahyadri Tiger Reserve (buffer zone)0.2
THDC Malshej Ghat PSPKalsubai-Harishchandragad WLS3
Humbarli Birmani PSPKoyna WLS (Sahyadri Tiger Reserve core)8.8
Malshej Ghat Bhorande PSPBhimashankar Wildlife Sanctuary10.8
Saidongar-2 PSP, MavalBhimashankar Wildlife Sanctuary14.5
Saidongar-1 PSP, KarjatBhimashankar Wildlife Sanctuary15.5
Ambegaon PSPBhimashankar Wildlife Sanctuary16
Shirawta PSPBhimashankar Wildlife Sanctuary19.7

Plateaus that look empty

Upper reservoirs need flat ground at the top of a cliff. In the Sahyadri, that means the lateritic plateaus, the sada. For most of the year they look bare. In the monsoon they flower.

The Naneghat plateau, next to Adoshi where Adani plans Bhorande's upper reservoir, holds 45ⓘ plant taxa found only in India. Adoshi and Ajnawale hold six threatened endemics, including the quillwort Isoetes dixitei. Reported On the Kas plateau, about 80ⓘ% of the region's significant plant species grow only on the plateau top and its cliffs. Documented

Because plateaus are often classed as "non-forest", their loss does not show up in the forest figures in Chapter 3.

Sacred groves

Maharashtra has thousands of devrai, groves protected by villages for their deity. One study counts about 2,800ⓘ. Reported Many hold the oldest trees left in their valley. The Adrai devrai near Khubi shelters Ceropegia anantii, a plant listed as Critically Endangered, and three other Ceropegia species grow about 200ⓘ metres from Adoshi. Reported No clearance paper we have read maps the devrai inside a project area.

A river still running free

The Kalu, below Malshej, is one of the last west-flowing rivers in the region without a dam. About half its watershed is dense forest, and it sustains the Katkari, a Particularly Vulnerable Tribal Group. The Supreme Court has stayed a dam on it. Reported Bhorande would lift water from the Kalu to a reservoir near the Kukadi basin on the other side of the crest.

Karjat, Bhivpuri, Shirawta and Warasgaon are open-loop designs: one of their reservoirs sits on a river, and the river's fish, flow and floods become part of the machine. Documented

Citizen scientists in Murbad taluka alone have logged more than 5,500ⓘ observations of over 1,600ⓘ species, including the rusty-spotted cat, striped hyena and Malabar trogon. Reported None of them is in an EIA.

Habitat · WPA 1972 Schedule I

14 Schedule-I mammals in Karjat's study area

The project's own EC lists leopard, sloth bear, Indian wolf, four-horned antelope and pangolin among 14 Schedule-I mammals, and orders a human–animal conflict plan.

Documented Karjat EC

Wildlife corridor

Bhimashankar–Malshej–Sahyadri forest corridor

A contiguous forest linkage used by leopard, sambar, gaur, Shekru and langur. Karjat lies within it even though it is outside the sanctuary's legal line.

Reported Karmactive (WII attribution to verify)

Species · Maharashtra state animal; WPA Schedule I

Shekru (Indian giant squirrel)

Lives in Bhimashankar's canopy near Karjat. Canopy fragmentation from submergence and transmission lines cuts its tree-to-tree routes.

Reported ThePrint

Plateau · 45 Indian endemic plant taxa (Naneghat)

Naneghat and Adoshi plateaus

Naneghat holds 45 Indian endemic plant taxa; Adoshi and Ajnawale plateaus hold six threatened endemics including Isoetes dixitei. Bhorande's upper reservoir is planned on Adoshi.

Reported Sanctuary Asia (citing Rahangdale 2014)

Sacred grove · Critically Endangered endemic

Adrai sacred grove and Ceropegia anantii

A devrai near Khubi shelters the Critically Endangered Ceropegia anantii; three Ceropegia species grow ~200 m from Adoshi.

Reported Sanctuary Asia

River

Kalu River

One of the region's last free-flowing west-flowing rivers; about half its watershed is dense forest. It sustains the Katkari, a Particularly Vulnerable Tribal Group. The Supreme Court has stayed a dam on it.

Reported Sanctuary Asia

Wildlife corridor

Harishchandragad–Bhimashankar corridor at Khubi

Khubi, site of THDC's upper reservoir, links two wildlife sanctuaries; flamingos, leopard, sambar and barking deer recorded.

Reported Sanctuary Asia

Protected area

Kalsubai-Harishchandragad Wildlife Sanctuary

THDC's Malshej PSP is 3 km away.

Reported Superkalam

Habitat

Murbad taluka biodiversity record

Citizen scientists have logged 5,500+ observations of 1,600+ species, including rusty-spotted cat, striped hyena, leopard and Malabar trogon.

Reported Sanctuary Asia (iNaturalist project)

Sacred grove

Sacred pools, temple forests and community fish sanctuaries

Western Ghats PSPs threaten sacred groves, sacred river origins and community-protected fish pools.

Reported SANDRP

Habitat

Muck, blasting and landslide-prone slopes

Karjat alone will excavate 110.78 lakh m³ of rock and dump 65.69 lakh m³ at three sites, on slopes where its EC requires landslide prevention. Raigad has seen deadly landslides (Taliye 2021, Irshalwadi 2023).

Documented Karjat EC

Habitat

What PSP construction does to mountain ecosystems (review)

A systematic review found PSP construction causes habitat loss, invasive plants, altered hydrology and poorer water quality.

Documented Normyle & Pittock 2019

Rock, blast and slope

Building a pumped storage plant means tunnelling through a mountain. Karjat alone will excavate 110.78ⓘ lakh cubic metres of rock and dump 65.69ⓘ lakh cubic metres of it as muck at three sites, on slopes where its own EC demands landslide prevention. Documented Raigad district remembers Taliye in 2021 and Irshalwadi in 2023, where hillsides came down on villages.

The Western Ghats are home to at least 325ⓘ globally threatened species. Documented The question this chapter leaves is simple: what does a "9.6 hectares per GWh" figure measure, when what is lost is a corridor, a plateau, a grove and a river?

Did you know?

About 65%Documented“…cies found in the Western Ghats, 352 (54%) are endemic. Animal diversity is also exceptional, with amphibians (up to 179 species, 65% endemic), reptiles (157 species, 62% endemic), and fishes (219 species, 53% endemic).…”UNESCO World Heritage Centre: Western Ghats of the Western Ghats' amphibians, and 54%Documented“…of the 4-5,000 plant species recorded in the Ghats is very high: of the nearly 650 tree species found in the Western Ghats, 352 (54%) are endemic. Animal diversity is also exceptional, with amphibians (up to 179 species, 65% endemic), reptiles (157 species, 62%…”UNESCO World Heritage Centre: Western Ghats of its tree species, are found nowhere else on Earth.

Documented Source: UNESCO World Heritage Centre: Western Ghats

Chapter 3

The forest bill

Every pumped storage project in the Ghats arrives with a bill paid in land. Some of it is farmland bought from families. Much of it is forest.

Project by project

14 projects in the Western Ghats have published both how much forest they need and how much energy they store. Together they need 1,331.2 hectares of forest for 139.1 GWh of storage. Documented

  • Karjat (Torrent): 233ⓘ ha of forest out of 377ⓘ ha.
  • Bhavali (JSW): 243.74ⓘ ha, the most forest per unit of storage of any project on record. The forest committee has deferred it twice.
  • Shirawta (Tata Power): 160.783ⓘ ha of the 197.797ⓘ ha it needs is forest, most of it reserved forest.
  • Amba (NTPC): 112.56ⓘ ha.
  • Warasgaon–Warangi (Adani): 90ⓘ ha, after its forest need rose and it was rejected once (Chapter 4).
  • Bhorande, Malshej Ghat (Adani): 60.877ⓘ ha, not counting the plateau where the upper reservoir would sit, which is classed as non-forest.

The largest project proposed in the state, JSW's 5,400ⓘ MW scheme in Bhor and Mahad, needs 645.62ⓘ ha, of which 241.22ⓘ ha is forest. Documented

1 dot = 1 ha of forest land
Data table
ProjectForest (ha)Trees
Bhavali PSP243.7–
Saidongar-1 PSP, Karjat23348,557
Shirawta PSP160.864,729
Aruna Kolamb PSP128.9–
Amba PSP112.6–
Warasgaon–Warangi PSP90–
Aruna PSP73.6–
Pane PSP66.9–
Malshej Ghat Bhorande PSP60.935,000
Savitri PSP55.6–
Humbarli Birmani PSP49.5–
Saidongar-2 PSP, Maval35.69,554
Bhivpuri PSP20.16,834

Per unit of storage

To compare projects of different sizes, I divide forest by storage. Across the 14 projects, the average is 9.6 hectares of forest per GWh. The methodology shows the formula and every input.

The spread matters more than the average. Adani's Tarali project in Satara needed forest at first and was redesigned to use 0ⓘ ha. Tata's Bhivpuri needs only 20.14ⓘ ha. Siting is a choice, and it changes the forest bill many times over.

ha of forest per GWh of storage

Bhavali PSP 22.1 Aruna Kolamb PSP 17.5 Shirawta PSP 14.9 Saidongar-1 PSP, Karjat 13.6 Amba PSP 12.6 Warasgaon–Warangi PSP 10 Aruna PSP 8.2 Pane PSP 7 Malshej Ghat Bhorande PSP 6.8 Humbarli Birmani PSP 5.3 Saidongar-2 PSP, Maval 4.9 Savitri PSP 3.7 Bhivpuri PSP 3.4 Tarali PSP 0
┆ Average: 9.6
Data table
ProjectForest (ha)GWhha of forest per GWh of storage
Bhavali PSP243.71122.1
Aruna Kolamb PSP128.97.417.5
Shirawta PSP160.810.814.9
Saidongar-1 PSP, Karjat23317.113.6
Amba PSP112.68.912.6
Warasgaon–Warangi PSP90910
Aruna PSP73.698.2
Pane PSP66.99.67
Malshej Ghat Bhorande PSP60.996.8
Humbarli Birmani PSP49.59.35.3
Saidongar-2 PSP, Maval35.67.24.9
Savitri PSP55.615.13.7
Bhivpuri PSP20.163.4
Tarali PSP09.80

If the whole pipeline looked like this

Maharashtra has signed MoUs for 78,215 MW. At 6 hours each, that is about 469 GWh. At the average above, it would need roughly 4,500 hectares of forest. This is an illustration of scale, not a forecast: many MoUs will never be built, and better siting would lower it.

What the bill leaves out

Paper figures tend to grow. When forest officers inspected MEIL's Ghosla site, its forest land went from 29.5ⓘ ha to 65.35ⓘ ha. Documented Warasgaon's went from 24.5ⓘ to 88.98ⓘ ha between applications. Documented

And the bill counts only land legally classed as forest. It leaves out:

  • plateaus classed as non-forest, which hold some of the rarest plants in the Ghats (Chapter 2);
  • private forest and farmland, roughly as large again;
  • the muck dumps, roads and transmission lines that cut through the forest that remains;
  • the forest carbon released, which no project nets out of its "green" claims.

Did you know?

Shirawta's forest has canopy density 0.7Documented“0.7 (Very Dense Forest) of Eco Class I and 64729 number of trees are”FAC (Advisory Committee) minutes, 8 May 2026, MoM ID FC/MOM/AC/969417/2026, page92 · 8 May 2026, 'very dense forest', and 64,729 treesDocumented“0.7 (Very Dense Forest) of Eco Class I and 64729 number of trees are”FAC (Advisory Committee) minutes, 8 May 2026, MoM ID FC/MOM/AC/969417/2026, page92 · 8 May 2026 are to be felled. The FAC still recommended Stage-I approval.

Documented Source: FAC (Advisory Committee) minutes, 8 May 2026, MoM ID FC/MOM/AC/969417/2026

Chapter 4

How the review was sidestepped

India's rules for a project like this are long. A developer needs a ToR, an EIA, a public hearing, an environmental clearance (EC) from the Expert Appraisal Committee, forest clearance in two stages, and the consent of forest-dwelling communities. Each step is meant to be a chance to say no, or to say "not here".

None of the steps below is illegal on its own. Together, they turn a review into a formality. Every item links to the document it comes from on the shortcuts page.

Rules that bend

Resettlement "not applicable". The 2013 land acquisition law requires a rehabilitation plan for affected families. Karjat's draft EIA says no plan is needed, citing a 2014 Maharashtra notification that applies R&R only to private purchases of 1,000ⓘ hectares or more. The project needs 377ⓘ hectares. Documented

Outside the line, inside the habitat. Wildlife clearance and stricter scrutiny apply near protected areas. Karjat is described as 16ⓘ km from Bhimashankar and outside its eco-sensitive zone, so it needed no wildlife clearance. Its own EC lists 14ⓘ Schedule-I mammals in the study area. Documented

A reserve that is only "proposed". The forest committee found most of Karjat's forest inside the proposed Rajmachi Conservation Reserve and cleared it because the reserve is not yet notified (Chapter 1). Documented The Western Ghats ESA, which would also cover Karjat, has been issued in draft six times since 2014 and never made final. Reported The Gadgil panel wanted 64ⓘ% of the Western Ghats treated as ecologically sensitive; the Kasturirangan group cut it to 37ⓘ%. Reported A protection that stays a draft protects nothing.

Rejection that does not stick

Adani's Warasgaon–Warangi was rejected by the EAC on 27 September 2024 after its forest need more than tripled. A fresh ToR was granted on 31 December 2024. Documented Rejection was a delay, not a no.

Experts say the EAC almost never rejects a project. Himanshu Thakkar of SANDRP calls its rejection rate "practically zero" and says it does no assessment of options. Reported

Copy, paste, clear

The ToR conditions for THDC's Humbarli Birmani ask for Stage-I clearance of 55.64ⓘ ha of forest. That is the Savitri project's figure; Humbarli needs 49.5ⓘ ha. Documented The EAC visited NTPC's Amba site in June, before the rains, saw cactus and dry streams, and concluded the reservoirs "will enhance moisture content". Documented

Never the whole valley

No cumulative impact study exists for the Kal, Savitri, Pej, Kalu or Koyna basins. Documented Each project is assessed alone, as if the next valley were empty. Pane's upper dam is about 3ⓘ km from Warasgaon's. The upper reservoirs of NTPC's Amba and Avaada's Pawana Falyan, appraised separately, are about 1.5ⓘ km apart. Documented

Rules being rewritten

Drilling as "forest activity". The Forest Advisory Committee recommended in July 2024 that exploratory drilling for hydro and pumped storage be treated as forest activity, needing no clearance, with felling of up to 100ⓘ trees. Documented Whether it has been notified is not confirmed.

Loosening the limits. The Central Electricity Authority's roadmap of January 2026 proposes allowing pumped storage in eco-sensitive zones that are not yet notified and within 10ⓘ km of protected areas, a lighter "White Category" for off-river projects, and relaxed Western Ghats conditions. Documented These are proposals, not law.

Fast-track from the top. In November 2025 the Chief Minister promised a "fast-track mechanism" for time-bound clearances, environmental approvals included. In March 2026 he ordered time-bound rollout of all 55ⓘ MoUs. Official claim The approvals were promised before the assessments were done.

A green label. Pumped storage is classed as renewable energy. That brings green certificates, priority lending and transmission waivers, without counting the forest carbon lost or checking what power is used to pump the water (Chapter 7). Documented

  1. The 2013 land acquisition law (RFCTLARR) requires a rehabilitation and resettlement plan for affected families.

    Resettlement declared 'not applicable' Documented
    Documents ↗

  2. Wildlife clearance and stricter scrutiny apply to projects near protected areas.

    Outside the sanctuary line, inside the habitat Documented
    Documents ↗

  3. Rejection by the Expert Appraisal Committee should force a lower-impact redesign.

    Rejected in September, back in December Documented
    Documents ↗

  4. Cumulative impact and carrying-capacity studies show what many projects do to one basin together.

    Project by project, never the valley Documented
    Documents ↗

  5. Eco-sensitive zones, the 10 km buffer around protected areas, and Western Ghats conditions limit where projects can go.

    Proposal to loosen the rules themselves Documented
    Documents ↗

  6. Any non-forest use of forest land needs prior clearance under the Forest (Conservation) Act.

    Drilling redefined as 'forest activity' Documented
    Documents ↗

  7. Environmental and water approvals are meant to be independent assessments.

    Fast-track promised before the projects are assessed Official claim
    Documents ↗

  8. Green incentives should reward net environmental benefit.

    A 'green' label that ignores the forest Documented
    Documents ↗

  9. No construction before environmental and forest clearance and a public hearing.

    Works on the ground before clearance (alleged) AllegedNot yet reviewed
    Documents ↗

  10. An EIA must survey the actual site's species and river.

    Baseline data from the wrong river ReportedNot yet reviewed
    Documents ↗

  11. Tree enumeration fixes the compensation and the scale of felling.

    Three different tree counts Reported
    Documents ↗

  12. Unused acquired land should revert to owners under the 2013 Act.

    Land taken for one dam, reused for another (alleged) AllegedNot yet reviewed
    Documents ↗

  13. The EAC should independently test projects, including whether they are needed.

    A regulator that 'practically' never says no Reported
    Documents ↗

What I checked and did not find

Activists have said the EAC skipped site visits before granting ECs. In September 2024 the EAC said a site visit would be carried out "wherever possible" for the 15ⓘ projects proposed in the Western Ghats. I checked the minutes: visits to Bhivpuri, Shirawta, Karjat and Pane are on record before their ECs. We mark that claim as not supported and keep it in the data with the reason. Whether a visit was enough is another question: at Karjat, the sub-committee judged the upper reservoir from the developer's drone footage, because it could not reach the site. Documented

Did you know?

The Western Ghats Ecologically Sensitive Area has been issued as a draft six times since 2014 and never made final. Maharashtra's share is 17,340Reported“Overall, the notification proposes to declare 56,825.7 sq km as ecologically sensitive, including 449 sq km in Gujarat, 17,340 sq km in Maharashtra, 1,461 sq km in Goa, 20,668 sq km in Karnataka, 6,914 sq km in Tamil Nadu, and 9,993.7 sq km in Kerala.”Onmanorama: sixth draft ESA notification (3 Aug 2024) sq km.

Reported Source: Onmanorama: sixth draft ESA notification (3 Aug 2024)

Chapter 6

The promise

Why so many projects, so fast? Because Maharashtra has promised a great deal of storage.

By March 2026 the state had signed about 55ⓘ MoUs for 78,215ⓘ MW of pumped storage. Official claim The Chief Minister said six of them, 10,300ⓘ MW in all, had their project reports approved by the Central Electricity Authority. Official claim

Today about 400ⓘ MW actually runs in the state: Bhira (150ⓘ MW) and Ghatghar (250ⓘ MW). Documented

Signed in MoUs 78,215 MWDocumented“…eting, Maharashtra has signed 55 MoUs with various companies to develop pumped storage projects with a total proposed capacity of 78,215 MW. The projects are expected to attract an investment of around ₹4,16,701 crore and generate nearly 1,27,990 employment opportun…”Electrical Mirror: CM review of 55 PSP MoUs Tracked on this site 60,615 MW Operating today 400 MWDocumentedDerived on this siteBhira 150 MW + Ghatghar 250 MW.Wikipedia: Bhira Hydroelectric Project (150 MW pumped storage unit)
Saidongar-1 PSP, Karjat · Forest clearance granted Saidongar-2 PSP, Maval · Study terms approved (ToR) Bhivpuri PSP · Under construction Shirawta PSP · Environmental clearance granted Bhira PSP (existing) · Operating Ghatgar PSP (existing) · Operating Bhavali PSP · Forest clearance deferred Pane PSP · Environment clearance recommended Malshej Ghat Bhorande PSP · Study terms approved (ToR) THDC Malshej Ghat PSP · Study terms approved (ToR) JSW Bhor–Mahad PSP (5,400 MW) · Study terms approved (ToR) Tarali PSP · Environmental clearance granted Warasgaon–Warangi PSP · Rejected, resubmitted Patgaon PSP · Study terms lapsed (ToR) Koyna–Nivakane PSP · Environment clearance recommended Pimpalpada–Savale PSP · Study terms approved (ToR) Kumbhe PSP · Study terms approved (ToR) Ambegaon PSP · Study terms approved (ToR) Savitri PSP · Study terms approved (ToR) Kamod PSP · Study terms approved (ToR) Adnadi PSP (Chikhaldara) · Study terms approved (ToR) Amba PSP · Study terms approved (ToR) Aruna PSP · Study terms approved (ToR) PEN Off-Stream PSP · Study terms approved (ToR) Tilari PSP · Study terms approved (ToR) Pawana Falyan PSP · Study terms approved (ToR) Kolhapur PSP (Chandgad) · Study terms approved (ToR) Nayagaon PSP (Soygaon) · Study terms approved (ToR) Ghosla PSP · Study terms approved (ToR) Humbarli Birmani PSP · Study terms approved (ToR) Aruna Kolamb PSP · Study terms approved (ToR) Ghatghar PSP Stage II · Study terms deferred (ToR) Kalu PSP · Study terms approved (ToR) Ranavadi PSP · Study terms approved (ToR)

Operating (2)Cleared or being built (6)MoU or ToR stage (22)Deferred, lapsed or rejected (4)

Locator only: dots are placed by latitude and longitude. A full map with forests and protected areas comes later.

Where the projects stand

This site tracks 39 projects with 60,615 MW between them, 50,815 MW of it in the Western Ghats. Most are at an early stage: 23 have a ToR, which lets them start their EIA. A handful have an EC or forest clearance. One, Karjat, has started cutting. The projects page lists every one, sorted by trees and forest first.

An MoU is a promise, not a permit. But in this pipeline the promise has a way of arriving before the review. Rithwik's 1,200ⓘ MW Chandgad project got its ToR recommendation in March 2023, more than two years before the state signed its MoU. Documented And because the projects are reviewed one at a time (Chapter 4), nobody has asked how many of them the Sahyadri can hold.

Did you know?

Maharashtra has signed about 55Documented“Maharashtra Pumped Storage Power Projects: 55 MoUs Fast-Tracked”Electrical Mirror: ensure fast implementation of 55 MoUs, page55 · 13 April 2026 PSP MoUs for 78,215 MWDocumented“…eting, Maharashtra has signed 55 MoUs with various companies to develop pumped storage projects with a total proposed capacity of 78,215 MW. The projects are expected to attract an investment of around ₹4,16,701 crore and generate nearly 1,27,990 employment opportun…”Electrical Mirror: CM review of 55 PSP MoUs. Only about 400 MWDocumentedDerived on this siteBhira 150 MW + Ghatghar 250 MW.Wikipedia: Bhira Hydroelectric Project (150 MW pumped storage unit) actually runs today: Bhira (150 MWDocumented“…Specifications [ edit ] The plant's maximum output capacity is nominally 300 MW , generated by six 25 MW Pelton turbines and a 150 MW pumped storage generator added in 1997. In 2014 two 10 kW microturbine units were added to generate further power from the t…”Wikipedia: Bhira Hydroelectric Project (150 MW pumped storage unit)) and Ghatghar (250 MWDocumented“dated 10.06.1985 to the existing project Ghatghar 2x125MW PSP. The committee”2 × 125 MW = 250 MW.EAC 52nd meeting minutes, 13 Apr 2026, page4 · 13 April 2026).

Documented Source: Wikipedia: Bhira Hydroelectric Project (150 MW pumped storage unit) · EAC 52nd meeting minutes, 13 Apr 2026: existing Ghatghar 2x125 MW PSP · CEA: PSP development in country (Jun 2024) · Electrical Mirror: CM review of 55 PSP MoUs

Chapter 7

A battery that can burn coal

A pumped storage plant does not make electricity. It stores it, and it loses some along the way.

Diagram of a pumped storage plant: an upper reservoir on a forested plateau joined by a tunnel to a powerhouse and a lower reservoir in the valley. 🐸🦜🐿️ Upper reservoir Lower reservoir Tunnel Turbines Grid

☀️ Daytime: power is cheap

When solar floods the grid at midday, pumps push water from the lower reservoir up a tunnel to the upper one. The hill becomes a battery.

🌙 Evening: power is dear

When demand peaks, the water falls back through turbines and makes electricity. About 22% of the energy is lost on the round trip.

🪓 The cost: the forest

Two reservoirs, a dam, tunnels, muck dumps, roads and power lines go onto forested hills. On record so far: 1,64,674 trees to be felled, from the 5 projects whose tree count is public, and 3,211 ha of forest land across 32 of the 39 projects.

🐸 The cost: life around it

Reservoirs and roads break up plateaus, streams and wildlife corridors that hold species found nowhere else, and take village land and grazing.

Less comes out than goes in

Every unit used to pump water uphill returns about 77.5% when the water comes down. Documented That is the round-trip efficiency in Tamil Nadu's 2026 tariff order, the best contractual figure in India. The rest is lost to friction, pumps and turbines.

If the projects tracked here ran at the rate Karjat's EC expects, they would deliver about 162 TWh a year and lose about 47 TWh a year doing it. That is about 2.7% of everything India generated in FY2025-26. This is a model, not a measurement; the methodology shows how.

In (pumping): 100 Out (generating): 77.5 Lost: 22.5

It depends on what charges it

Storage moves emissions in time. Whether it cuts or adds CO₂ depends on which power plants run more when it pumps, and which run less when it generates.

On today's grid the plants that change output first are mostly coal. If coal pumps the water and the stored power displaces coal later, every MWh delivered adds about 0.28 tonnes of CO₂, because of the loss. Across the pipeline that is up to 45 million tonnes a year. This is an upper bound, not a forecast.

If instead the pump uses solar power that would otherwise be wasted, storage cuts emissions, by about -0.88 tonnes per MWh once the plant's own construction is counted. That is the case for storage, and it is a real one.

The break-even is simple: storage cuts emissions only when more than 22.5% of the pumping energy is solar that would otherwise be thrown away, or 29.4% once construction is counted.

0.28

tonnes of CO₂ added per MWh delivered

Break-even solar share: 22.5%

What is missing

Developers state the CO₂ their projects will "avoid". Official claim Those claims assume every unit of pumping power is clean. No project I have read commits to publishing what time of day it pumps, or from what. Without that, nobody can say whether a given plant is a solar battery or a coal battery. And none of the "avoided" figures subtracts the forest carbon lost in Chapters 1 to 3.

Did you know?

A pumped storage project uses more electricity than it gives back. At 77.5%DocumentedDerived on this site“In its order dated April 30, the commission adopted a tariff discovered through competitive bidding, fixing an annual fixed charge of Rs 123 lakh per MW with a declared cycle loss of 22.5%, resulting in a total annual storage cost of Rs 150.675 lakh per MW.”100% − 22.5% cycle loss = 77.5% round-trip efficiency.DT Next: TNERC approves tariff for 500 MW pumped storage round-trip efficiency, 22.5Documented“In its order dated April 30, the commission adopted a tariff discovered through competitive bidding, fixing an annual fixed charge of Rs 123 lakh per MW with a declared cycle loss of 22.5%, resulting in a total annual storage cost of Rs 150.675 lakh per MW.”TNERC PSP tariff order 2026 (22.5% cycle loss) of every 100 units used for pumping are lost.

Documented Source: TNERC PSP tariff order 2026 (22.5% cycle loss) · NREL ATB 2023: round-trip efficiency 70–87%

Chapter 8

Built, not used, and cheaper options

Built and never used

A pumped storage plant only helps if it pumps. Gujarat's 240ⓘ MW Kadana ran a pump-mode trial in 2004–05 and has not pumped since. Sardar Sarovar's 1,200ⓘ MW has never pumped at all. Documented Both are still counted as pumped storage in national plans.

Cost that climbs

Big tunnels in hard mountains run late and over budget. Australia's Snowy 2.0, first priced in 2017, now has a target cost of A$22.2ⓘ billion plus contingency, up to A$25ⓘ billion: more than 12ⓘ times that first estimate. Reported The Western Ghats are geologically different, but the lesson about underground risk travels.

A$ billion

First estimate, 2017 A$2 bnReported“Snowy Hydro 2.0 cost could blows out to $25 billion — more than 12 times original cost of $2 billion | The Nightly”The Nightly Target cost, Oct 2026 A$22.2 bnReported“…The Federal Government-owned Snowy Hydro has confirmed an updated target cost to complete the project would conservatively cost $22.2b “with an allowance for a cost scenario of $25 billion”, following a cost reassessment from principal contractor Future Generatio…”The Nightly With contingency A$25 bnReported“Snowy Hydro 2.0 cost could blows out to $25 billion — more than 12 times original cost of $2 billion | The Nightly”The Nightly
Data table
First estimate, 20172
Target cost, Oct 202622.2
With contingency25

Batteries have caught up

Battery prices have fallen fast. Put on the same basis, rupees per MWh of storage capacity per year, recent Indian tenders give ₹8.6–14.3 lakh for battery storage and ₹9.7–13.6 lakh for pumped storage. Documented The ranges overlap. Batteries sit on a few hectares of already-cleared land, are built in months rather than years, and can go next to the solar parks they serve.

A tariff is a price, not the full cost, and batteries and eight-hour pumped storage do somewhat different jobs. The methodology lists every tender and its limits.

₹ lakh per MWh of storage capacity per year

Battery storagePumped storage

Data table
Tenderh₹ lakh/MW/yr₹ lakh/MWh/yr
RVUNL 4-h BESS434.28.6
JSW–UPPCL PSP 8-h877.29.7
SECI PSP-I 8-h (fixed)8109.113.6
GUVNL 2-h BESS227.813.9
MSEDCL 2-h BESS (2 GW/4 GWh)228.714.3

Sites that are not forest

Even for pumped storage, the Sahyadri forest is not the only place to build. Existing reservoirs can be paired: Ghatghar Stage II would add 125ⓘ MW on 7.04ⓘ ha. Documented Tarali was redesigned off forest land altogether (Chapter 3). Old mines and off-river sites outside the Ghats exist. The order should be: brownfield and existing reservoirs first, non-forest off-river sites next, Ghats forest last, if at all.

  1. Old mines and brownfield land No Maharashtra proposal yet
  2. Existing reservoirs Ghatghar PSP Stage II: 7 ha forestDocumented“around 9.78 hectares, out of which 7.04 hectares are anticipated to be forest land, while”EAC 52nd meeting minutes, 13 Apr 2026 (item 52.1), page40 · 13 April 2026
  3. Non-forest, off-river sites Tarali PSP: 0 ha forestDocumented“Forest Land : 0 ha”Tarali EC, page13
  4. Ghats forest, last if at all Saidongar-1 PSP, Karjat: 233 ha forestDocumented“for diversion of 233 ha. forest land for construction of Saidongar-I Karjat Off-”FAC (Advisory Committee) minutes, 8 May 2026, MoM ID FC/MOM/AC/969417/2026 (Saidongar-1 change of CA land), page97 · 8 May 2026

Did you know?

Tata Power says Bhira, where a 150 MWOfficial claim“Bhira, Maharashtra 150 MW pumped hydro storage project; 1997”Tata Power: our pumped hydro history pumped storage unit was added in 1997 to a 1927 hydro station, was Asia's first pumped hydro storage project.

Official claim Source: Tata Power: our pumped hydro history

Chapter 9

What supporters say

Pumped storage has serious advocates, and the grid does need storage. Here is their case, in their terms.

  • It lasts. Dams and tunnels run for many decades; developers speak of lifetimes up to eighty years. Batteries need replacing every twelve to fifteen. Official claim
  • It steadies the grid. Spinning turbines give inertia, frequency control, black start and fast ramping that keep a grid with a lot of solar stable. Official claim
  • Low life-cycle emissions. Studies find closed-loop pumped storage has among the lowest life-cycle emissions of any storage, about 86 g CO₂e per kWh in NREL's base case, when it is charged with clean power. Documented
  • Built at home. Civil works and much of the equipment are Indian; less lithium has to be imported. Official claim
  • It is needed. India already wastes solar power at midday for lack of storage, and the evening peak is growing. Reported
  • A long record. Tata Power says Bhira, where a 150ⓘ MW pumped storage unit was added in 1997, was Asia's first. Official claim

Torrent says the Karjat project will avoid millions of tonnes of CO₂ a year, use less land than conventional hydro, and plant more trees than it fells. Official claim The Chief Minister says the projects bring clean power for peak demand and have completed their approvals. Official claim The Minister of State for Power, Meghna Bordikar, says Karjat was approved after "complying with all conditions" of the environment ministry. Official claim

My reply, in one line

All of this holds for well-sited, closed-loop projects charged with surplus solar. None of it requires the Sahyadri forest.

Did you know?

Bare-looking lateritic plateaus bloom in the monsoon. On the Kas plateau, about 80%Documented“Almost two thirds of over 100 phytogeographically significant species occur on the plateau top; these represent 26 plant families and 43 genera. About 80% of the species are restricted to the upper plateau and its escarpments.”Watve (2013), Kas plateau endemic plant diversity of the region's significant plant species grow only on the plateau top and its cliffs.

Documented Source: Watve (2013), Kas plateau endemic plant diversity

Chapter 10

What I ask for

Storage is needed. Forest is not a fair price for it. I ask for:

  1. Stop the felling at Saidongar until an independent, ground-checked tree count is published and the felling order is made public.
  2. Assess the valley, not the project. Cumulative impact and carrying-capacity studies for the Kal, Savitri, Kundalika, Ulhas–Pej, Kalu and Koyna basins before any further EC or forest clearance.
  3. Publish every EAC site-visit report for Western Ghats projects, and no EC without one.
  4. Keep projects out of the forest that matters most: no project parts in draft-ESA villages, eco-sensitive zones or wildlife corridors, and a limit on forest per GWh. Build on brownfield sites and existing reservoirs first.
  5. Reject the proposed relaxations for un-notified eco-sensitive zones, the buffer around protected areas, and the Western Ghats conditions.
  6. Ask first. Free, prior and informed consent from the gram sabha under the Forest Rights Act and PESA before a ToR, not after an EC. Hearings in the affected villages, with time to prepare, and EIAs in Marathi. Close the R&R loophole.
  7. Prove the charge. Hourly data on when and from what each plant pumps, an audited carbon figure, and a green label only for plants charged with surplus renewable power.
  8. Track what is built. Public pumping and generation data for every plant, starting with Bhira, Ghatghar, Kadana and Sardar Sarovar.
  9. Compare options. A required comparison with batteries and brownfield sites for the same service, before any forest is diverted.
  10. Publish the MoU register, with locations, water allocations and status for every project.

Follow what happens next on the timeline and in the news. Every number in this story, with its source, is in the data.

Did you know?

The Western Ghats are older than the Himalaya. UNESCO says their forests shape the Indian monsoon itself.

Documented Source: UNESCO World Heritage Centre: Western Ghats