Saidongar-2 PSP, Maval

Study terms approved (ToR) (as of March 2026) · Torrent PSH4, now Torrent Energy Storage Solutions 3 (Torrent Power) · Inside draft ESA

1,200MW

9,554trees to be felled

35.6ha of forest land

2villages named

  1. MoU signed
  2. Study terms (ToR)
  3. Forest clearance
  4. Construction
  5. Operating
Trees 9,554 Documented“to the reservoir. This project will require 35.60 ha Forest land and cutting of about 9,554”Saidongar-2 draft EIA executive summary (MPCB): 'cutting of about 9,554 trees', page12 · March 2026 Documented
Forest (ha) 35.6 Documented“acquisition of 141.44 ha in which 35.60 ha is forest area and remaining 105.84 ha is”Saidongar-2 Maval draft EIA executive summary (MPCB), page10 · March 2026
Total land (ha) 141.44 Reported“23 Saidongar 2 – Maval Open Loop PSP (1200 Mw) (141.44 Ha) Torrent PSH 3 Pvt. Ltd. Raigarh/ Maharashtra Mula-Mutha/ Bhima/ Krishna 29 Jan. 2025 For ToR Approved”SANDRP: 2025 env & forest clearance decisions
Capacity (MW) 1,200 Documented“Notification and amendments thereof, the proposed Saidongar 2 - Maval PSP (1200 MW)”Saidongar-2 Maval draft EIA executive summary (MPCB), page1 · March 2026
Storage (GWh) 7.2 (estimate) Documented“The Saidongar 2 - Maval Open Loop Pumped Storage Project (PSP) is a 1200 MW (7200 MWH)”EAC 31st meeting minutes, 14 May 2025 (Saidongar-2 site-visit report, Annexure II), page137 · 14 May 2025
Location18.9000°N, 73.4472°E (exact)Documented“7. Upper Reservoir Latitude -18°53'60"N”Saidongar-2 Maval draft EIA executive summary (MPCB), page2 · March 2026
DistrictPune, Raigad, Maval, Karjat
VillagesKusur, Pali
Nearest protected areaBhimashankar Wildlife Sanctuary, 14.45 km Official claim
MoU signed3 September 2024

Notes

  • Fresh Terms of Reference (ToR) The list of studies an EIA must cover, set by the expert committee. Getting a ToR is the first clearance step, not a permission to build. More in glossary → 18 Feb 2025 ( Expert Appraisal Committee (EAC) The central committee of experts that recommends ToR and EC for river valley and hydro projects, including PSPs. More in glossary → 29 Jan 2025); Environmental impact assessment (EIA) The study a developer must commission on a project's effects on land, water, wildlife and people before it can get an EC. More in glossary → filed for Public hearing A meeting near the project site, run by the state pollution control board, where affected people can object on record. More in glossary → Mar 2026; forest proposal FP/MH/HYD/IRRIG/556376/2025.
  • Upper reservoir at Kusur (Maval); the lower reservoir on the Pej is shared with Saidongar-1 and its land is counted there. 35.60 ha forest of 141.44 ha.
  • The EAC sub-committee that visited Saidongar-1 on 21–23 Apr 2025 also covered this site (report considered 14 May 2025): Upper Reservoir 2 was 'not accessible by road or foot' and was seen only on drone footage; the approach road takes 15.09 ha of the 35.60 ha forest.
  • Storage MW, MWh and GWh MW is how fast power flows; MWh (or GWh = 1,000 MWh) is how much energy is stored or delivered. More in glossary → implied from 6 h generation.

Timeline

Category
  1. · Felling Documented #

    Maval Pumped storage project (PSP) Two reservoirs at different heights: water is pumped up when power is cheap and released through turbines when power is needed. More in glossary → draft EIA: 35.6 ha of forest and about 9,554 trees

    Details and documents

    Torrent's draft EIA for the 1,200 MWDocumented“Notification and amendments thereof, the proposed Saidongar 2 - Maval PSP (1200 MW)”Saidongar-2 draft EIA executive summary (MPCB), page1 · March 2026 Saidongar-2 (Maval) project, filed for public hearing, puts forest land at 35.60 haDocumented“acquisition of 141.44 ha in which 35.60 ha is forest area and remaining 105.84 ha is”Saidongar-2 draft EIA executive summary (MPCB), page10 · March 2026 of 141.44 haDocumented“acquisition of 141.44 ha in which 35.60 ha is forest area and remaining 105.84 ha is”Saidongar-2 draft EIA executive summary (MPCB), page10 · March 2026 and says about 9,554 treesDocumented“to the reservoir. This project will require 35.60 ha Forest land and cutting of about 9,554”Saidongar-2 draft EIA executive summary (MPCB), page12 · March 2026 will be cut. It shares its lower reservoir with the Karjat project.Documented“acquisition of 141.44 ha in which 35.60 ha is forest area and remaining 105.84 ha is”Saidongar-2 draft EIA executive summary (MPCB), page10 · March 2026

    Saidongar-2 PSP, Maval · Saidongar-2 draft EIA executive summary (MPCB)

  2. · Clearance Documented #

    EAC considers site-visit report for Karjat PSP

    Details and documents

    A three-member sub-committee (EAC chair G. J. Chakrapani, member Ajay Kumar Lal, MoEFCC's Krishnendu Mondal) visited Saidongar-1 and -2 on 21–23 Apr 2025. It walked the lower reservoir on the Pej but saw both upper reservoirs only on Torrent's drone footage, as they were not accessible, and called them barren table-land. Its five recommendations were narrower approach roads (17 haDocumented“diversion (17 Ha out of 233 Ha proposed forest land) and should be reflected in the final layout.”EAC 31st meeting minutes, 14 May 2025 (site-visit reports, Annexures I and II), page131 · 14 May 2025 of Karjat's 233 haDocumented“non-forest land and 233.0 hectares is forest land. Consequently, diversion of forest land is required,”EAC 31st meeting minutes, 14 May 2025 (site-visit reports, Annexures I and II), page128 · 14 May 2025 forest), CWLW-approved wildlife plans, monsoon-only water draw, a Muck disposal Rock and soil dug out for tunnels and caverns, dumped on land set aside for it. More in glossary → plan, and putting site-visit assurances in the EIA. The EAC accepted the report on 14 May 2025.

    Saidongar-1 PSP, Karjat · Saidongar-2 PSP, Maval · EAC 31st meeting minutes, 14 May 2025 (site-visit reports, Annexures I and II) · SANDRP: 2025 decisions (table of EAC minutes)

  3. · Clearance Reported #

    EAC recommends ToR for Saidongar-2 Maval and Ghosla

    Details and documents

    Same meeting as Saidongar-1 Karjat's ToR. Kamod's ToR application was withdrawn after parameters changed and approved on 12 Mar.

    Saidongar-2 PSP, Maval · Ghosla PSP · Kamod PSP · SANDRP: 2025 env & forest clearance decisions

  4. · MoU signed, no clearance yet Reported #

    Torrent signs Memorandum of understanding (MoU) A non-binding agreement between the state and a developer to study and build a project at a site, with a water allocation. More in glossary → for Karjat, Maval and Junnar PSPs (5,700 MW)

    Details and documents

    All three sites described as off-stream with six hours of daily storage; ₹27,000 crore over five years.Reported“Torrent Power Limited has signed a memorandum of understanding (MoU) with the Government of Maharashtra for development of three pumped storage hydro projects of 5,700 MW capacity in Maharashtra.”Power Line

    Saidongar-1 PSP, Karjat · Saidongar-2 PSP, Maval · Junnar PSP · Power Line

Sources

Confidence: verified