Bhavali PSP

Forest clearance deferred (as of 2 December 2025) · JSW Energy (PSP Two)

1,500MW

Not disclosedtrees to be felled

243.74ha of forest land

4villages named

  1. MoU signed
  2. Study terms (ToR)
  3. Environment clearance
  4. Construction
  5. Operating
Forest (ha) 243.74 Documented“The project area is 274.82 ha. and forest land required to be diverted is 243.74 ha of which 181.45 ha in”EAC 32nd meeting minutes, 29 May 2025, page85 · 29 May 2025
Total land (ha) 278.92 Documented“Bhavali Pumped Storage Project (1500 MW) in an area of 278.92 Ha in Village Kalbhonde, Kothale”EAC 32nd meeting minutes, 29 May 2025, page2 · 29 May 2025
Capacity (MW) 1,500 Reported“…rial region. This , even as share of renewable energy goes up will help ensure grid stability and power at all times. --> The 1500MW /11017 MWh Bhavali Pumped Storage facility at Igatpuri in Maharashtra is now back on the anvil with the Expert Appraisal Commit…”Bhavali PSP approval for EIA study
Storage (GWh) 11.02 Reported“…ion. This , even as share of renewable energy goes up will help ensure grid stability and power at all times. --> The 1500MW /11017 MWh Bhavali Pumped Storage facility at Igatpuri in Maharashtra is now back on the anvil with the Expert Appraisal Committee of th…”Bhavali PSP approval for EIA study
Cost (₹ crore) 8,964.02 Documented“ix. Project Cost: The estimated project cost is Rs. 8964.02 Crores. Total capital cost earmarked towards”EAC 30th meeting minutes, 30 Apr 2025 (Bhavali EC, item 30.1), page3 · 30 April 2025
Location19.6088°N, 73.5959°E (exact)Documented“Upper Reservoir: 19°36'31.69" N ,73°35' 45.06" E;”EAC 32nd meeting minutes, 29 May 2025 (item 32.1), page2 · 29 May 2025
DistrictNashik, Thane, Igatpuri, Shahapur
VillagesJamunde, Ladewadi, Kalbhonde, Kothale
MoU signed2021

Sources disagree

Status

Annexure 1 says construction has started. No Stage-I FC found after the Dec 2025 deferral; works may be on non-forest land. Unresolved.

Notes

  • Environmental clearance (EC) The environment ministry's permission for a project, given after the EIA and public hearing, with conditions attached. More in glossary → recommended 29 May 2025; Forest Advisory Committee (FAC) The central committee that recommends whether forest land may be diverted for a project. More in glossary → deferred 2 Dec 2025.
  • PESA and Fifth Schedule areas In tribal-majority 'Scheduled Areas', the 1996 PESA Act gives gram sabhas a say over land acquisition and resources. More in glossary → ; 10 families displaced, 130 affected.

Timeline

Category
  1. · Rejection Documented #

    FAC defers Bhavali a second time

    Details and documents

    The FAC again deferred the diversion of 243.74 haDocumented“Diversion of 243.74 ha. (Shahapur Division 181.45 ha and West Nasik Division 62.29 H”FAC minutes, 27 Feb 2026 (MoM FC/MOM/AC/749302/2026), page22 · 27 February 2026 of forest (181.45 haDocumented“Diversion of 243.74 ha. (Shahapur Division 181.45 ha and West Nasik Division 62.29 H”FAC minutes, 27 Feb 2026 (MoM FC/MOM/AC/749302/2026), page22 · 27 February 2026 Shahapur, 62.29 haDocumented“Diversion of 243.74 ha. (Shahapur Division 181.45 ha and West Nasik Division 62.29 H”FAC minutes, 27 Feb 2026 (MoM FC/MOM/AC/749302/2026), page22 · 27 February 2026 West Nashik) for JSW's Bhavali Pumped storage project (PSP) Two reservoirs at different heights: water is pumped up when power is cheap and released through turbines when power is needed. More in glossary → , 'for seeking additional information'.

    Bhavali PSP · FAC minutes, 27 Feb 2026 (MoM FC/MOM/AC/749302/2026)

  2. · Rejection Documented #

    Forest Advisory Committee defers Bhavali PSP (243.74 ha forest)

    Details and documents

    The project in a Scheduled Area of Igatpuri–Shahapur needs 243.74 haDocumented“10 Bhavali PSP (1500 MW) JSW Energy PSP Two Limited Thane & Nasik/ Maharashtra Bham/ Darna/ Godavari 02 Dec. 2025 Non-forestry use of 243.74 ha. (Shahapur Division 181.45 ha and West Nasik Division 62.29 Ha) of forest land Deferred: More Information Sought”SANDRP: 2025 decisions of forest, the highest per MW, MWh and GWh MW is how fast power flows; MWh (or GWh = 1,000 MWh) is how much energy is stored or delivered. More in glossary → among projects with data.

    Bhavali PSP · SANDRP: 2025 decisions

  3. · Clearance Official claim #

    CEA concurrence Technical-economic approval of a hydro DPR by the Central Electricity Authority, needed above a cost threshold. More in glossary → concurs DPRs for Bhivpuri and Bhavali

    Details and documents

    First CEA concurrences for new Maharashtra PSPs: Tata's 1,000 MWOfficial claim“…Ps) with a cumulative capacity of 2.5 GW in Maharashtra. While the 1500 MW Bhavali PSP is being developed by JSW Energy Ltd., the 1000 MW Bhivpuri PSP is being developed by Tata Power Co. Ltd. These PSPs are concurred with the support of the Central Water Commissi…”Energetica: CEA concurs 2,500 MW of PSPs in Maharashtra · 23 September 2024 Bhivpuri and JSW's 1,500 MWOfficial claim“…or milestone by concurring two more Pumped Storage Projects (PSPs) with a cumulative capacity of 2.5 GW in Maharashtra. While the 1500 MW Bhavali PSP is being developed by JSW Energy Ltd., the 1000 MW Bhivpuri PSP is being developed by Tata Power Co. Ltd. These PS…”Energetica: CEA concurs 2,500 MW of PSPs in Maharashtra · 23 September 2024 Bhavali, concurred within 10Official claim“…ission (CWC), Geological Survey of India (GSI), and Central Soil and Materials Research Station (CSMRS) and were concurred within 10 days of completion of the DPRs i.e. the date on which the complete DPRs were submitted on the online portal by the developers. Th…”Energetica: CEA concurs 2,500 MW of PSPs in Maharashtra · 23 September 2024 days of complete DPRs. Commissioning promised by 2028.

    Bhivpuri PSP · Bhavali PSP · Energetica: CEA concurs 2,500 MW of PSPs in Maharashtra

  4. · MoU signed, no clearance yet Reported #

    JSW signs Memorandum of understanding (MoU) A non-binding agreement between the state and a developer to study and build a project at a site, with a water allocation. More in glossary → for the Bhavali PSP

    Details and documents

    1,500 MWReported“…uery and hit enter: Homepage Green Energy Green Energy Bhavali Pumped Storage Moves Ahead With Approval for EIA study The 1500MW /11017 MWh Bhavali Pumped Storage facility at Igatpuri in Maharashtra is now back on the anvil with the Expert Appraisal Commit…”iamrenew: Bhavali pumped storage moves ahead with approval for EIA study at Igatpuri (Nashik–Thane). The Terms of Reference (ToR) The list of studies an EIA must cover, set by the expert committee. Getting a ToR is the first clearance step, not a permission to build. More in glossary → stage that followed proposed diverting 212 haReported“…ect. The state forest department received a proposal from JSW Energy PSP, a wholly-owned subsidiary of JSW Neo Energy, to divert 212 hectares of land for the project. As per a cost-benefit analysis, the net present value (NPV) of the land has been calculated at…”iamrenew: Bhavali pumped storage moves ahead with approval for EIA study, of which 62.42 haReported“…ted at about Rs 24.5 crore. The forest land proposed for diversion lies within the revenue boundaries of Jamunde village, Nashik (62.42 hectares), and Kalbondhe and Kothale villages, Thane (150.23 hectares). The total number of trees to be cut for the project will…”iamrenew: Bhavali pumped storage moves ahead with approval for EIA study of forest in Jamunde, Nashik, and 150.23 haReported“…ersion lies within the revenue boundaries of Jamunde village, Nashik (62.42 hectares), and Kalbondhe and Kothale villages, Thane (150.23 hectares). The total number of trees to be cut for the project will be determined during the EIA study. I am Renew Next Despit…”iamrenew: Bhavali pumped storage moves ahead with approval for EIA study in Kalbondhe and Kothale, Thane (as reported).

    Bhavali PSP · iamrenew: Bhavali pumped storage moves ahead with approval for EIA study

Consent and voices

Displacement ReportedNot yet reviewed

In a Scheduled Area, 10Reported“There shall be 130 affected families of which 10 shall be displaced families. The acquisition”EAC 30th meeting minutes, 30 Apr 2025 (Bhavali EC), page112 · 30 April 2025 families face displacement and 130Reported“There shall be 130 affected families of which 10 shall be displaced families. The acquisition”EAC 30th meeting minutes, 30 Apr 2025 (Bhavali EC), page112 · 30 April 2025 are affected; no Gram sabha The assembly of all adult voters of a village; under FRA and PESA its consent is needed for some decisions on land and forests. More in glossary → consent process has been sought.

Said by Research dossier (FAC/Parivesh records)
📍 Kalbhonde, Kothale, Jamunde (Igatpuri/Shahapur)
Sources (1)