Humbarli Birmani PSP
1,500MW
Not disclosedtrees to be felled
49.5ha of forest land
2villages named
- MoU signed
- Study terms (ToR)
- Environment clearance
- Forest clearance
- Construction
- Operating
| Forest (ha) | 49.5 Documented“ix. Land requirement: Total land requirement of the project is 334.82 ha (Forest: 49.50”EAC 52nd meeting minutes, 13 Apr 2026 (item 52.2), page43 · 13 April 2026 |
|---|---|
| Total land (ha) | 334.82 Documented“ix. Land requirement: Total land requirement of the project is 334.82 ha (Forest: 49.50”EAC 52nd meeting minutes, 13 Apr 2026 (item 52.2), page43 · 13 April 2026 |
| Capacity (MW) | 1,500 Documented“construction of the project Humbarli Birmani Off Stream(1500MW) in Village: Hatlot, Taluka:”EAC 58th meeting minutes, 15 Jul 2026 (Humbarli Birmani ToR, item 58.5), page311 · 15 July 2026 |
| Storage (GWh) | 9.26 Documented“Capacity / Cultural command area (CC 1500 MW/9255 MWH pumped storage compone”EAC 52nd meeting minutes, 13 Apr 2026 (item 52.2), page6 · 13 April 2026 |
| Cost (₹ crore) | 8,470.89 Documented“estimation the tentative cost of project is INR 8470.89 Crores.”EAC 52nd meeting minutes, 13 Apr 2026 (item 52.2), page49 · 13 April 2026 |
| Location | 17.8618°N, 73.6109°E (exact)Documented“Upper Reservoir Coordinates: 17o 51' 42.63 "N, 73o 36' 39.37 "E”EAC 52nd meeting minutes, 13 Apr 2026 (item 52.2), page6 · 13 April 2026 |
| District | Satara, Ratnagiri, Mahabaleshwar, Khed |
| Villages | Hatlot, Birmani |
| Nearest protected area | Koyna WLS (Sahyadri Tiger Reserve core), 8.82 km Documented |
| MoU signed | 3 September 2024 |
Sources disagree
Capacity (MW)
- 1,000 Documented EAC 52nd meeting minutes (MoU figure)
- 1,500 Documented EAC 52nd meeting minutes (ToR proposal)
MoU amendment from 1,000 to 1,500 MW was in progress at the time of the ToR application.
Notes
- Expert Appraisal Committee (EAC) The central committee of experts that recommends ToR and EC for river valley and hydro projects, including PSPs. More in glossary → 52nd meeting (13 Apr 2026, item 52.2) deferred the Terms of Reference (ToR) The list of studies an EIA must cover, set by the expert committee. Getting a ToR is the first clearance step, not a permission to build. More in glossary → .
- The upper dam and intake at Hatlot fall inside the Mahabaleshwar–Panchgani Eco-sensitive zone (ESZ) A notified buffer around a sanctuary or national park where some activities are banned or regulated. More in glossary → (S.O. 52(E), 2001), which allows only non-polluting industry; hydel plants over 50 MW are CPCB 'red' category, so the EAC told THDC to get the ESZ monitoring committee's No-objection certificate (NoC) A letter from another authority saying it does not object, often required before a committee will consider a project. More in glossary → first (applied 18 Feb 2026).
- Lower reservoir 3.3 km from the Western Ghats / Sahyadri The 1,600 km mountain chain along India's west coast: older than the Himalaya, a UNESCO World Heritage site and a global biodiversity hotspot. More in glossary → Wildlife sanctuary (WLS) and tiger reserve Protected areas under the Wild Life (Protection) Act. A tiger reserve has an inviolate core and a surrounding buffer. More in glossary → buffer; both villages in the draft Western Ghats Ecologically Sensitive Area (ESA) About 56,825 sq km of the Western Ghats proposed for protection since 2014; still only a draft, reissued six times. More in glossary → .
- WRD's original 400 MW site was inside the tiger reserve and was dropped. 334.82 ha, 49.50 ha forest; 1,500 MW / 9,255 MW, MWh and GWh MW is how fast power flows; MWh (or GWh = 1,000 MWh) is how much energy is stored or delivered. More in glossary → ; Muck disposal Rock and soil dug out for tunnels and caverns, dumped on land set aside for it. More in glossary → 78.34 lakh m³.
- Memorandum of understanding (MoU) A non-binding agreement between the state and a developer to study and build a project at a site, with a water allocation. More in glossary → of 3 Sep 2024 was for 1,000 MW.
- Coordinates are the upper reservoir.
- The Mahabaleshwar–Panchgani ESZ Monitoring Committee took up THDC's NoC request on 15 Apr 2026 and granted it on 6 Jul 2026; the EAC then recommended ToR on 15 Jul 2026 (58th, item 58.5).
- The ToR condition on Forest clearance (Stage-I / Stage-II) Central permission to use forest land for a project. Stage-I is in-principle approval with conditions; Stage-II is final approval. More in glossary → in those minutes reads '55.64 ha', which is Savitri's forest figure, not Humbarli's 49.50 ha.
Timeline
-
EAC recommends ToR for Humbarli Birmani after ESZ NoC
Details and documents
With the ESZ committee's NoC in hand, the EAC recommended ToR for THDC's project. Its Stage-I FC condition cites 55.64 haDocumented“obtaining Stage I FC for 55.64 ha of forest land involved in the project shall be”EAC 58th meeting minutes, 15 Jul 2026 (item 58.5), page312 · 15 July 2026 of forest, Savitri's figure, not Humbarli's 49.50 haDocumented“related works for project is 334.82 ha out of which Forest area is 49.50 ha and non-forest”EAC 58th meeting minutes, 15 Jul 2026 (item 58.5), page309 · 15 July 2026.
-
Mahabaleshwar–Panchgani ESZ committee clears Humbarli Birmani
Details and documents
The ESZ Monitoring Committee granted THDC a no-objection certificate for a 1,500 MWDocumented“construction of the project Humbarli Birmani Off Stream(1500MW) in Village: Hatlot, Taluka:”EAC 58th meeting minutes, 15 Jul 2026 (item 58.5), page311 · 15 July 2026 project whose upper dam lies inside the eco-sensitive zone. The EAC had deferred the ToR in April for want of it.
-
EAC defers Humbarli Birmani Pumped storage project (PSP) Two reservoirs at different heights: water is pumped up when power is cheap and released through turbines when power is needed. More in glossary → : upper dam inside Mahabaleshwar–Panchgani ESZ
Details and documents
52nd meeting. THDC's 1,500 MWDocumented“amendment of the MoU for Humbarli Birmani PSP from 1000 MW to 1500 MW is currently”EAC 52nd meeting minutes, 13 Apr 2026 (item 52.2), page10 · 13 April 2026 project (334.82 haDocumented“ix. Land requirement: Total land requirement of the project is 334.82 ha (Forest: 49.50”EAC 52nd meeting minutes, 13 Apr 2026 (item 52.2), page43 · 13 April 2026, 49.50 haDocumented“ix. Land requirement: Total land requirement of the project is 334.82 ha (Forest: 49.50”EAC 52nd meeting minutes, 13 Apr 2026 (item 52.2), page43 · 13 April 2026 forest) puts its upper dam inside an eco-sensitive zone that allows only non-polluting industry. The EAC said it was not a fit case for ToR until THDC gets the ESZ monitoring committee's NOC.
Sources
- EAC 52nd meeting minutes, 13 Apr 2026 (item 52.2) · 13 April 2026
- Renewable Watch: THDC MoU for six PSPs (6,790 MW) · 4 September 2024
- EAC 58th meeting minutes, 15 Jul 2026 (Humbarli Birmani ToR, item 58.5) · 15 July 2026